Sutton, Massachusetts residents fighting $16 billion data center proposed by Kraft Group

Posted

Sutton, Massachusetts residents are taking action to kill a proposal for a mega data center there, ahead of the town's timeline.

A petition with 346 signatures gathered by resident Shawn Buzzell was filed with the town clerk for certification Tuesday morning. It's calling for a special town meeting.

"At that special town meeting we would be voting to amend the town's zoning bylaws. As part of the petition, we've defined what a data center is. We've prohibited them from classifying themselves as anything else under acceptable use and then we're amending the table of use regulations in town to prohibit it's development and construction in all zones in town," Buzzell told WBZ-TV.

Sutton town leaders have been scrambling to research and respond to a $16 billion proposal for a data center campus backed by United Global Packaging Group and The Kraft Group, which are both affiliated with New England Patriots owner Robert Kraft. The data center would bring in millions in revenue and lower property taxes. But critics worry about the impact on the environment, public health, and home values.

"We don't have town water. So we have an aquifer under the town and the amount of water that a data center might use is phenomenal," said Sutton resident Robert Dufault. He went to town hall Tuesday to sign the petition.

"I would hate to see Sutton sell its soul," he told WBZ. 

If the town pursues a moratorium, it would hit the pause button on the project for a year, preventing any permissions on development while a bylaw is carefully created. Any decision would ultimately require a two-thirds majority vote at a town meeting.

Buzzell's petition would give voters that opportunity early next year.

"I wouldn't say that the entire town is blanket opposed to data centers. The beautiful thing about this amendment is it allows us to still go back to the table, we can amend, we can define what we do want in the community, instead of being told what we should have," Buzzel said.

The planning board expects guidance from the state on data center regulations by the end of this year. The town is also looking for larger spaces in Sutton to host these crowded meetings.

Sutton, Massachusetts is about 48 miles west of Boston and ten miles south of Worcester. The data center campus is proposed for a property off Boston Road and Providence Road.

Under the current plan there would be ten buildings. The first two would open in 2029, and two more would open every year through 2033. 

The town has a website for anyone looking for information on the project.  

Local News, Syndicated Local